Scottish Water Treated Water Storage Refurbishment

Client: Scottish Water

Project value: £660,757

Location: Angus, Scotland

Timeframe: October 2022 - April 2023

A Treated Water Storage asset that has undergone structural refurbishment

Background

This Scottish Water Treated Water Storage (TWS) asset is part of the distribution network serving treated water to the Angus area, east Scotland. This project is part of a large programme of structural refurbishment works on TWS assets to maintain the highest levels of water quality. The client had concerns that this asset may not be suitable for refurbishment, due to the nature of construction and the inherent risk of potential ingress.

The roof and returns are formed by corrugated steel sheets which are secured sandstone walls. There is also a cladding system situated in between the roof and sandstone walls to prevent ingress into the tank.

Challenge

During the excavation works to fully expose the cladding, Mackenzie Construction discovered significant points of potential ingress through the existing cladding system. For operational reasons, Scottish Water stressed that this tank needed to be online as soon as possible to avoid putting strain on the network. Due to the construction of the roof, conventional methods of repair could not be applied to this asset. There was an option of installing a new tank roof, however, this would incur considerably increased costs, increase carbon emissions and would require external and internal approval of the design, causing delays on the project and further stress on the network. Therefore, we had to innovate and examine other remedial options.

Solution

The solution that MCL developed was to design & install a new bespoke cladding system which would be installed between the existing roof structure and the protruding sandstone walls. The depth of the drainage had to be increased as the existing level was found to be contributing to ingress issues. We increased the drainage depth down to 1.2m to prevent ingress issues.

Following the installation, a flood test was conducted which demonstrated the success of our intervention. Shortly after, the site experienced a heavy downpour of rain which further proved our intervention of bringing the water level 1.2m below ground level as no ingress was reported following an internal inspection.

This project breathed new life into the asset for another 20 years and beyond. Through working in collaboration with the client we have saved a significant amount of the money needed in building a new asset or installing a new tank roof. Our solution also reduced carbon emissions compared to the alternative options, working towards our Net Zero Goals.

This successful case study acts as inspiration for future projects and continues to drive our teams to innovate in our race to Net Zero.