Mitcheldean TWS Refurbishment

Client: Severn Trent Water

Sector: Water

Project value: £1.5M

Location: Mitcheldean, Gloucestershire

Timeframe: January - October 2025

As part of the Severn Trent Water (STW) Framework, Mackenzie Construction Ltd (MCL) was appointed to refurbish treated water storage (TWS) assets in Gloucestershire, England.

For all projects within the framework, MCL fulfils the roles of both Principal Designer and Principal Contractor, overseeing safe and compliant delivery from concept to completion.

The Mitcheldean project involved the refurbishment of a live treated water reservoir roof, ensuring continued regulatory compliance with Drinking Water Inspectorate (DWI) standards and long-term asset resilience.

The project has now been fully completed and handed back to Severn Trent Water. Upon successful delivery, STW awarded MCL an additional two tank refurbishment projects in the same location.

Scope of works

The project centred on the inspection, removal and replacement of the waterproofing system on a live treated water service reservoir. Ensuring the tank remained fully operational throughout was critical, requiring tightly controlled work sequencing and strict contamination prevention measures.

Existing conditions
The reservoir roof was originally protected by a loose‑lay membrane. Beneath this, the team identified:
• Teram geotextile layer
• 50mm Kingspan insulation
• A Proofex-type waterproofing membrane
• Primer layer over the concrete slab

Initial preparations
To prepare the site and protect water quality:
• Full edge protection was installed along the roof perimeter.
• Vermin mesh was fitted to prevent wildlife from entering the roof zone.

Weather management measures
Because the reservoir was live and contained treated water, the existing waterproofing could not be removed during rainfall. To mitigate this constraint:
• MCL procured and installed large inflatable encapsulation tents to create weatherproof working environments.
• These controlled spaces allowed work to continue safely during adverse weather events.

Execution of works
• Works were completed in carefully controlled sections to safeguard the exposed concrete structure.
• Continuous weather monitoring ensured that only dry conditions were used for membrane removal.
• During wet periods, all activity moved under the encapsulation tents.
• Once prepared, the new Proofex 3000 membrane was installed across the full 3,300m² roof.
• MCL undertook their own spark testing before engaging the STW‑approved third‑party assurance tester, who found minimal defects which was an excellent result for such a large area.

Following waterproofing, the team conducted a structural assessment confirming the roof could support the planned 1,600 tonnes of stone backfill, in line with STW standards. The roof was then fully reinstated, backfilled, and the asset returned to operational service.

Impact

The successful delivery of the TWS roof refurbishment provides significant long-term benefits:

Operational reliability

The new waterproofing system ensures the treated water asset remains protected and compliant with DWI regulations, supporting resilient water supply.

Enhanced asset life

Quality installation, spark-tested assurance and robust backfill reinstatement extend the lifespan of the reservoir.

Innovation in delivery

Use of inflatable encapsulation tents showcased MCL’s proactive problem-solving approach, reducing downtime and demonstrating strong programme control.

Environmental & Safety Excellence

Strict adherence to contamination controls, environmental disposal standards and safe working practices ensured zero incidents throughout the project.